Transportation Improvement Program

The Transportation Improvement Program (TIP) is an intermediate range planning document that reflects the transportation expenditures that are planned to be spent over the next four years. Project details are provided, such as project description, cost, funding source, and funding year. The TIP contains information on planning studies, road improvements, and transit. It is updated every four years.

Record of Adoption and Changes

  • April 26, 2018 – TIP adopted by HTMPO Policy Committee
  • July 26, 2018 – Amended to included $100,000 for the Terrebonne Comprehensive Plan – Transportation Element.
  • July 26, 2018 – Amended to include various projects requested by DOTD.
  • October 4, 2018 – Administrative modification to include performance measures adopted at the July 2018 Policy Committee meeting, a narrative on project selection process, and text showing how selected projects help accomplish the performance measures.
  • October 25, 2018 – Amended to include Good Earth Transit’s 2019 Program of Projects and to accept the performance targets included in Good Earth Transit’s Asset Management Plan. The Policy Committee also authorized to amend for funding for other various small transit agencies pending DOTD approval of their grant applications.
  • November 16, 2018 – Administrative modification to change funding source for Greyhound Intercity Bus operations from 5310 to 5311. Also to move the construction phase of H.013250 US 90: LA 308 -23 MI E LA182 from FFY 2020 to FFY 2019.
  • January 24, 2019– Amendment to include feasibility phases for H.011962 LA1: Company Canal MB-Lockport (HBI); H.013818 LA 308: Byu Lafourche MB-Golden Med. (HBI); and H.011986 LA 58: Bayou Terrebonne MB Rehab (HBI) in FFY 2019. Also to include LA DOTD’s Transit Asset Management Performance Targets and updates highway safety performance targets for 2019.
  • July 25, 2019– Amendment to include H.009320 Acadian Road Roundabout right-of-way and utility relocation phases in FY 19-20 at $3.5 million and $100K respectively. Amendment to remove H.013272 Lafourche Multiuse Path. Administrative modification to reduce construction cost of H.013250 to $7.1 million and move to FFY 20. Administrative modification to move the construction phase of H.009320 Acadian Road Roundabout to FFY 20.
  • October 24, 2019 – Amendment to include Airport Connector Road and Bridge construction costs in FY 2020. Amended to include Good Earth Transit’s 2020 Program of Projects. Administrative modification to add project number and update name of H.013940 LA 648 & N Acadia Rd Intersection Study. Administrative modification to move H.012338 Civic Center Sidewalk construction from FFY 2019 to FFY 2020.
  • April 27, 2020 – Administrative modification to change construction funding year for H.013340 Valhi Blvd, Multi-Use Trail, Phase 1 from FFY 2020 to FFY 2021.
  • May 14, 2020 – Administrative modification to change construction funding year for H.012339 LA 24 Sidewalk Rehab from FFY 2019 to FFY 2020.
  • July 6, 2020 – Administrative Modification updating the construction cost estimate for H.012338 Civic Center Sidewalks from $367,500 to $226,000; adjust timing for H.013340 Valhi Blvd. Multi Use Trail Phase 1 Engineering from FFY 2019 to FFY 2020 and Construction from FFY 2020 to FFY 2021; and moving H.013429 Downtown Thibodaux Sidewalks construction from FFY 2019 to FFY 2021.
  • July 8, 2020 – Administrative Modification changing the name for H.013940 LA 648 & Acadia Road Intersection Study to LA 648 & Acadia Road Intersection Improv.
  • July 15, 2020 – Administrative Modification making the following changes:
    • H.013493 Washington Street Sidewalks moving design phase from FFY 2020 to FFY 21 and construction phase from FFY 21 to FFY 22
    • H.013269 Audubon Ave Overlay moving design phase from FFY 19 to FFY 21 and construction phase from FFY 21 to FFY 22.
    • H.013429 Downtown Thibodaux Sidewalks moving construction phase from FFY 21 to FFY 22.
    • H.013403 LA 20 & LA 304 Sidewalk Imp moving design phase from FFY 19 to FFY 22 and construction phase from FFY 20 to FFY 22.
    • H.013404 LA 1 Sidewalks (Cut Off) moving design phase from FFY 19 to 21 and construction phase from FFY 20 to FFY 22.
    • H.013402 LA 1 & LA 308 Ped & Multiuse Path (Lockport) moving environmental phase from FFY 19 to FFY 21, design phase from FFY 20 to FFY 21, and construction phase from FFY 21 to FFY 22.
    • H.013490 Central Lafourche Multi-Use Path Ph 1A moving design and environmental phases from FFY 20 to FFY 21 and right-of-way phase from FFY 21 to FFY 22.
    • H.013340 Valhi Blvd Multi-Use Trail, Phase 1 moving design phase from FFY 20 to FFY 21 and construction phase from FFY 21 to FFY 22.
    • H.013453 Bayou Blue Sidewalks moving design phase from FFY 19 to FFY 22, right-of-way from FFY 20 to FFY 22, and construction from FFY 21 to FFy 22.
    • H.009320 Acadian Road Roundabout moving construction phase from FFY 20 to FFY 21.
  • July 23, 2020 – Amended to include right-of-way and utility relocation phases for H.013402 La 1 & La 308 Ped & Multiuse Path (Lockport) in FFY 2022.
  • August 7, 2020 – Administrative modification to move construction phases for H.012338 Civic Center Sidewalks and H.012339 LA 24 Sidewalk Rehab from FY 2020 to FY 2021.
  • Sept. 4, 2020 – Administrative modification to increase construction cost on H.011915 Airport Connector Road and Bridge to 35,673,000.00, and change one of the funding sources from State Bonds to Local.
  • Oct. 14, 2020 – Administrative Modification making the
    following changes:
    • H.013493 Washington Street Sidewalks design moved to FY 2022.
    • H.013500 Dr. Martin Luther King Phase 1 design moved to FY 2022.
    • H.011962, Change project name from: LA 1: COMPANY CANAL MB-LOCKPORT (HBI) to: LA 1: CO CANAL MB REHAB (LOCKPORT) (HBI) & Move Feasibility phase from FFY 2019 to FFY 2021.
    • H.011986, Change project name from: LA 58: BAYOU TERREBONNE MB REHAB (HBI) to: LA 58: B TERREBONNE MB RH (MONTEGUT) (HBI) & Move Feasibility phase from FFY 2019 to FFY 2021.
    • H.012447, Change project name from: LA 182: BAYOU LAF BR AT RACELAND (HBI) to: LA 182: B LAFOURCHE MB RH (RACELAND) (HBI).
    • H.013818, Change project name from: LA 308: BYU LAFOURCHE MB-GOLDEN MED. (HBI) to: LA308: B LAFOUR MB RH (GOLDEN MEADOW) (HBI) & Move Feasibility phase from FFY 2020 to FFY 2021.
    • H.013940 648 & ACADIA ROAD INTERSECTION IMPROV construction phase cost is now $3.48M of STP<200K @ 80/20 in FFY 2022.
  • Oct. 22, 2020 – Amended H.013429 Downtown Thibodaux to add Design Phase in FY 21 for $19,320 (80/20; STP<200K). Also H.013940 LA 648 & Acadia Road Intersection Improvements to remove Feasibility/Stage 0 Phase and add ROW Phase in FY 22 for $100,000 (80/20; STP<200K).
  • October 19, 2020 – Administrative modification to H.013940 648 & ACADIA ROAD INTERSECTION IMPROV increasing right-of-way from $100,000 to $ $575,000 (80/20; STP <200K).